Quick morning update;
The lads have visited the site this morning to have a look at the concrete pad that was giving us trouble yesterday. They have decided that more concrete is needed on top to bring it to sit flush with the height of the existing pad. They've put some bolts in so that the new will bond well to the old, so its all good in the hood.
This does mean that we can't add the frame on this morning as we had hoped - so those that were heading down to do this this morning can just come along with everyone else at half twelve, hopefully will be set by then.
Entry #12: 1st November 2010
Most of our efforts are now based centrally at the site. There are a few members of the team still working back at the studio laser cutting logos for the cladding and promoting and selling the hoodies.
Site today was pretty muddy and it felt like we hadn’t done very much apart from discover issues. There were some steep variances in the heights of the feet - which puzzled us for a while - until we realised that they had been placed the wrong way round, all part of the fun!
The drilling for the resin bolts is the most time consuming currently. The 18v drills are pretty good and last a good while when your working on timber, but after attacking the holes on one pad of concrete the poor thing needs charging for a good couple of hours - just cant hack it.

Uploaded with ImageShack.us
We all stayed at site till the bitter end last night. The weather was pretty horrendous but we powered on through. We managed to get one frame up by the end of yesterday. Everything seams to take so much longer when we were doing it. The frame needed aligning and then drilling and because it was so tight we then had to use a mallet to bash the bolts through... One is up though, only a few more to go!

Uploaded with ImageShack.us
What really held us back was the left hand footing on the south frame. The ground is so soft because of the weather and the way that it has been sculpted, so the concrete just wobbles around. We have attempted to stabilise this by adding more concrete around the pad to support it.
This meant that we couldn't attach that frame till it was dry. We had to prop the North frame up last night before we left as it is supporting itself - windy conditions could easily be the end of it.
Hopefully it will still be there tomorrow - 4 days left to go!
Site today was pretty muddy and it felt like we hadn’t done very much apart from discover issues. There were some steep variances in the heights of the feet - which puzzled us for a while - until we realised that they had been placed the wrong way round, all part of the fun!
The drilling for the resin bolts is the most time consuming currently. The 18v drills are pretty good and last a good while when your working on timber, but after attacking the holes on one pad of concrete the poor thing needs charging for a good couple of hours - just cant hack it.
Uploaded with ImageShack.us
We all stayed at site till the bitter end last night. The weather was pretty horrendous but we powered on through. We managed to get one frame up by the end of yesterday. Everything seams to take so much longer when we were doing it. The frame needed aligning and then drilling and because it was so tight we then had to use a mallet to bash the bolts through... One is up though, only a few more to go!
Uploaded with ImageShack.us
What really held us back was the left hand footing on the south frame. The ground is so soft because of the weather and the way that it has been sculpted, so the concrete just wobbles around. We have attempted to stabilise this by adding more concrete around the pad to support it.
This meant that we couldn't attach that frame till it was dry. We had to prop the North frame up last night before we left as it is supporting itself - windy conditions could easily be the end of it.
Hopefully it will still be there tomorrow - 4 days left to go!
Entry #11: 30th October 2010
To catch up, a few keen beans went to the site today to push the feet along.
Joe was in charge today, so I caught up with him in the afternoon to find out how the day had gone...
The group managed to get 2 shoes finished - so these elements are now fixed to the concrete - they would have kept going but the drills ran out of battery - AGAIN!
Uploaded with ImageShack.us
4 of the frames have been properly fixed together, we didn’t want to do this poorly on Friday as we were worried that under tension the frames could snap, we do not want to have to buy more! They are done now and are ready to lift up into place when the feet have been completed.
We managed to get some filming done whilst the second shoe was being drilled - everyone was really optimistic but then the drills died, so - not as much got done as was hoped.
One positive was the weather, clear skies have allowed the site to dry out a little - it was turning into a slippy mud bath, health and safety nightmare - saws and drills flying everywhere...
So a big thanks go to our dedicated Saturday team; Pat, Aoife, Joe, John, Jess and Kawther. Hopefully we wont have to see the site next Saturday as we are still aiming for a Friday finnish, fingers, toes and everything crossed.
Uploaded with ImageShack.us
Subscribe to: